Diamondback Engineering working with Sidney, NE

Diamondback is excited to be working with Sidney, NE. Lauren Benton and David Hach completed Sidney's water system master planin 2014. Diamondback is finalizing the design and specifications for Phase I of the Master Plan. This includes the design of the East Booster Pump Station and 1.5 miles of suction piping. The Diamondback Team has been instrumental in securing project funding through the Nebraska State Revolving Loan Fund. Construction for Phase I is expected later in 2014. We're also excited to begin the design of Phase II of Sidney's water system improvements. This phase will include distribution piping and a 500,000 gallon water storage tank serving Sidney's high pressure zone.